IS THERE A PROJECT THAT YOU THINK WE WOULD BE INTERESTED IN, OR, JUST WANT TO SEND OUT A MESSAGE TO OUR ESTIMATING TEAM.  SEND AN EMAIL TO ESTIMATING@SML.CA .  WE WOULD LOVE TO HEAR FROM YOU!!!!

UVic - BWC Heat Recovery Failed System Renovation, Phase 3 - Closing August 26th, 2025

Project Name: UVic – RFT 273 – Bob Wright Centre (BWC) Heat Recovery Failed System Renovation, Phase 3

Project Location: UVic Bob Wright Centre, 3800 Finnerty Rd, Victoria, BC |

Project Description: Renovation Project: Replace Heat recovery Loop on the roof of the BWC (Bob Wright Centre) at UVic

Close Date: August 26th, 2025
Time: 2:00 pm MDT

LINK TO PROJECT FILES

Addenda: 00

Clarification: 00

OWNER: University of Victoria

TYPE OF CLOSING: Stipulated Price Bid

Tender Acceptance Period: 30 days

Bid Bond: by GC
Performance Bond: Provide Rates on Quotes over $1 Million
L&M Bond: Provide Rates on Quotes over $1 Million

Start Date: August 18th, 2025
Completion Date: December 31st, 2025

Warranty: 1 Year

Note: The lowest or any Tender will not necessarily be accepted.

Please provide bonding rates for all scopes over $1,000,000.00.

CH Hillhurst 1 Apartments Renovation - Closing September 3rd, 2025

Project Name: CH Hillhurst 1 Apartments Renovation

Project Location: 411 14 Street NW, Calgary, AB

Project Description: The Hillhurst 1 building is set to undergo an extensive rejuvenation that involves a variety of energy improvements, lifecycle upgrades, and performance and functionality enhancements. These upgrades will include building envelope improvements, including new exterior cladding, storefront glazing, windows, doors, and balcony railing enhancements; parkade upgrades; major mechanical and electrical services upgrades throughout the building including all new main switch gear and panels though out the units; landscaping improvements; and resident additions and along with a rejuvenation to the main floor.

Close Date: September 3rd, 2025
Time: 2:00 pm MDT

LINK TO PROJECT FILES

Addenda: 02

Clarification: 00

OWNER: Calgary Housing

TYPE OF CLOSING: Stipulated Price Bid

Tender Acceptance Period: 30 days

Bid Bond: by GC
Performance Bond: Provide Rates on Quotes over $1 Million
L&M Bond: Provide Rates on Quotes over $1 Million

Start Date: October 2025
Completion Date: December 2026

Warranty: 1 Year

Note: The lowest or any Tender will not necessarily be accepted.

Please provide bonding rates for all scopes over $1,000,000.00.

EIA North Tower Redevelopment - Closing September 26th, 2025

Project Name: EIA North Tower Redevelopment

Project Location: 1000 Airport Road, Edmonton International Airport, Edmonton, AB

Project Description: This project is for the redevelopment of the existing North tower at YEG. Edmonton Airport’s intention for the redevelopment of the North tower is to refresh the existing tower and allow for a more efficient, leasable office space for multiple office tenancies. The redevelopment includes the removal of hazardous materials in the building and the expansion of the existing floors of the North tower on the north and south sides to allow for a more typical and efficient office tenant fit out for each floor of the tower.

Close Date: September 26th, 2025
Time: 2:00 pm MDT

LINK TO PROJECT FILES

Addenda: 04

Clarification: 00

OWNER: Edmonton International Airport

TYPE OF CLOSING: Stipulated Price Bid

Tender Acceptance Period: 30 days

Bid Bond: by GC
Performance Bond: Provide Rates on Quotes over $1 Million
L&M Bond: Provide Rates on Quotes over $1 Million

Start Date: TBD
Completion Date: February 2028

Warranty: 1 Year

Note: The lowest or any Tender will not necessarily be accepted.

Please provide bonding rates for all scopes over $1,000,000.00.